Home Products Site Map Contact Us
Materials Handling Division
Industrial High Tolerance Floors
{short description of image} Advantages
{short description of image} Execution
{short description of image} Slab Stages of Construction
{short description of image} Screed Construction
{short description of image} Tools and Equipment
{short description of image} Reference List
Industrial and Domestic Doors
Docking System
Architectural Hardware
{short description of image}
Industrial High Tolerance Floors

High Tolerance Concrete Execution
Concrete floors should be laid under a cover of a roof in order to gain high quality & accuracy specially for production areas & storage areas. Casting & finishing in the open air may affect the shrinkage of the floor structure causing cracking & delimitation in addition to the risk of running the concrete surface by direct sun and/or rain.

1. Sub-grade & Sub-base:
Good construction of a concrete floor begins with a well- prepared sub-grade.Compacted granular soil sub-base is ideal for floor construction (Standard Proctor Test 95% minimum value).It is not recommended to cast floor slabs on plain concrete due to the risk of random early cracks because of bonding and different movements between old & newly laid concrete. Variations in levels of sub-base should not exceed 10mm.

2. Side Forms:
Side forms are fixed & leveled in position according to design to fit with the Long-Strip method of construction rather than the Chequer-Board Method which have been proved to make many problems in factories that have been operating due to the large no. & dimensions of the floor joints.

3. Water Proofing Slip Membrane:
This membrane should be used below the floor slab to secure slab movements without cracking and to prevent, hydration water from escaping to granular sub-base.

4. Floor Joints:
A good floor depends on its joints working as designed in addition to bringing their number to a minimum. Our flooring construction system is well recognized to be as if "Joint-less" this is due to our minimizing of joints in addition to the greatest care taken to insure perfect joint construction. Joints as described below are according to the designer/consultant recommendations as per included in the tender docoments.

Kinds of Joints:
a) Longitudinal or Construction Joints
These are the joints between the bays which were the positions of form construction. They are spaced according to racking system layout and/or machines layout Dowel or tie bars are inserted through our form construction to insure bonding between bays & also to secure settlement at bays edges. In some position where there is a doubt of settlement, a Tongue and Groove construction may be used.

b) Transverse Contraction Joints (Stress Release Joints):
These joints are formed by saw-cutting with a concrete diamond blade after concrete setting within 72hours.They are to be spaced according to design of the whole floor slabs by a spacing from 6-9m.These joints are of width 3-5mm.Their depth is made according to the whole floor slab depth e.g. 1" is enough for a slab 20cm. These joints are to be filled later on by an adequate joint sealant (min. after 28 days).

c) Isolation Joints:
These joints are constructed to insure full freedom of the whole floor slab & to neglect the effect of floor slab movements on the whole structure. They are constructed usually around Walls & Columns by fixing impregnated compressible board vertically against wall or base surface over full slab depth.

d) Expansion Joints:
Expansion joints are not normally required in floors constructed under cover of a roof unless they are very large.i.e., Floor Dimensions are more than 70m long. If any, they will have certain construction according to details & to be filled by an adequate joint sealant.It is recommended by the designer to place an expansion joint every 36.00m with dowel de-bonded bars, cut & chamfered according to specifications.

atural non metallic base origine or metallic origine in order to increase the resistance of the surface to abrasion & indeed increasing the durability & the non dusting proporties of the concrete floor surface with time.

{short description of image}

{short description of image}

{short description of image}

{short description of image}

More>>